- August 21, 2020
- Press Releases
LIBERTY Ostrava restarts Blast Furnace no. 2 following maintenance upgrades
• Restart of Blast Furnace No. 2 highlights the flexibility of the LIBERTY Ostrava business
• CZK 44 million of repairs to the Blast Furnace carried out during the shutdown period
After almost a four-month shutdown, LIBERTY Ostrava has restarted Blast Furnace No. 2 following essential repairs worth more than CZK 44 million to upgrade and modernise the furnace, which started its first campain almost 70 years ago. The restart highlights the ability of the LIBERTY Ostrava business to flex its operations in line with market demand.
Pascal Genest, CEO of LIBERTY Ostrava, said: “The temporary shutdown of the furnace allowed us to respond flexibly to the slump in steel demand due to the coronavirus pandemic and to reduce the metal inventory built for the start of the construction season. We are very pleased that the repairs have been carried out successfully and that we have been able to deliver on our commitment to restart the furnace by the end of August. The ability to manage the Blast Furnace in this way highlights the plant’s flexibility, which will help the business as it looks to improve its long term economic and environmental sustainability.”
After the furnace had cooled down for 40 days, from its normal 2,300 °C operating temperature, an extensive repair programme started. This programme included the replacement of the cooling piping, the modernization of the furnace cooling system as well as minor repairs to the hot-blast stoves, charging machines, skip tracks and the dust collector. A number of companies from the across the region, such as KADAMO, Stavby OMO, Hutní montáže Slovakia, and Speciální výškové práce – Roland Babka, supported the LIBERTY Ostrava team in effecting the repairs.
In line with an old steelmakers´ tradition, the Chief Smelter ignited the burners of the Blast Furnace with a torch lit by the fire from the other Blast Furnace. Václav Habura, Chief Operation Officer at LIBERTY Ostrava, explained: “The first tapping of hot metal will follow after about 20 hours of the restart, and it will take a few days for the furnace to produce hot metal which can be used for steelmaking.”
Blast Furnace no. 2, which is 35 meters high and whose structure measures 70 meters, was first lit on October 1, 1952. It can produce up to 3,200 tonnes of hot metal per day.
![]() |
![]() |
![]() |
![]() |
Further information from:
Barbora Černá Dvořáková Head of communications Liberty Ostrava |
+420 606 774 346 | barbora.cerna-dvorakova@libertysteelgroup.com |
Paddy Toyne-Sewell Head of Communications – Europe GFG Alliance |
+44 (0) 7767 498 195 | Patrick.toyne-sewell@gfgalliance.com |
Note to Editors:
LIBERTY Ostrava is an integrated steel business with an annual production capacity of approximately 3.6 million tonnes per annum serving construction, machinery and oil & gas industries. The company is a domestic leader in the manufacture of road barriers and tubes. In addition to the Czech market, it supplies its products to more than 40 countries around the world. Together with its subsidiaries in Ostrava, the company has 6,000 employees. The company manufactures its products with a minimum possible environmental footprint.
LIBERTY Steel Group is part of GFG Alliance, a collection of global businesses and investments owned by Sanjeev Gupta and his family. The Alliance is structured into three core industrial pillars; LIBERTY Steel Group, ALVANCE Aluminium Group and SIMEC Energy Group, independent of each other yet united through shared values and a purpose to create a sustainable future for industry and society. GFG Alliance employs c.35,000 people, across 10 countries and has revenues of >USD $20bn.
LIBERTY Ostrava a.s.
Barbora Černá Dvořáková
Head of Communicaions
T +420 595 683 390
M +420 606 774 346
barbora.cerna-dvorakova@libertysteelgroup.com
Latest News
View All
LIBERTY Ostrava’s mine supports underpinning the reconstruction of Prague’s sewer system
LIBERTY Ostrava is supplying 400 mine support arches to a major sewerage reconstruction project in Prague. It is one of...
View
Volunteers from LIBERTY Ostrava helped in eleven non-profit organizations
This autumn, 47 employees of LIBERTY Ostrava lent a hand in eleven socially beneficial organizations from Ostrava where they moved...
View
LIBERTY Ostrava and its unions agree 2023 CLA
The updated Collective Labour Agreement (CLA) will result in an 9.5% increase in LIBERTY Ostrava’s total payroll The company will...
View
LIBERTY Ostrava to provide 100 apprenticeships to young people from Ostrava’s vocational schools
LIBERTY Ostrava will welcome approximately one hundred apprentices from vocational secondary schools in Ostrava to try out their future profession...
View
Ostrava Steel Mine Supports
View
Thousands celebrate Family Day at LIBERTY OSTRAVA
Two thousand of LIBERTY Ostrava’s employees and their families have enjoyed the steelwork’s first Family Day event to be held...
View
LIBERTY Ostrava to invest CZK 88 million to halve dust emissions from sinter plant north
LIBERTY Ostrava is investing CZK 88 million on the installation of a new exhaust pipeline at its sinter plant north,...
View
LIBERTY Ostrava to distribute over CZK 500,000 to local community projects
LIBERTY Ostrava to support 21 local community projects nominated by employees this year Over eleven years the steelworks has distributed...
View
LIBERTY Ostrava to temporarily idle Blast Furnace No. 2 for repairs
LIBERTY Ostrava will temporarily idle its Blast Furnace No 2 to allow for a CZK 233 million (EUR 9.5m) repair...
View
LIBERTY Ostrava donate 200 thousand crowns to the Flamingos Ostrava parahockey team
Visitors to the Colours of Ostrava and the Festival in the Streets have helped the new Flamingos Ostrava parahockey team...
View